Tuesday, June 21, 2011

Good News!

Hello friends,
We have made a lot of progress with the help of some friends who came out and helped through the last few weeks. The whole house has been primed. All ceilings have been painted. All the trim that could be painted has been painted. Some need a second coat. Some of the rooms have been painted, some are in progress, others have yet to be started. We have a goal of getting everything done except for the flooring by the end of this month. It will be great if we can get flooring started early but that will have to wait till all the painting is finished. I have made a list of things left to be done below.
  1. Roll paint in all rooms (lots of walls!), second coat on some trim.
  2. Trim to install - crown molding, base, window stops
  3. Install remaining plumbing fixtures
  4. Tie in electrical lines for new room
  5. Cleanup - inside & outside
  6. Install flooring - stain and finish.
  7. Carpet install (will be done by carpet people)
  8. Cleanup - inside & outside
  9. Move in!!
Thanks to everyone who has been on site. We are very grateful for your sacrifice of time and service. May the Lord richly bless you for blessing us.
Shalom
Thomas & Tina

Sunday, May 29, 2011

House update

Hello friends,
We have been able to make some good progress in the renovation process. All the big 'construction' type work is finished. We have started painting the upstairs. There is some trim to be installed downstairs after which we can proceed with painting. A lot of cracks to caulk!
  1. Cleanup - inside & outside
  2. Trim to install - windows, doors, case the openings, crown molding
  3. Spray prime downstairs
  4. Spray paint trim downstairs
  5. Roll paint in all rooms
  6. Install remaining plumbing fixtures
  7. tie in electrical lines for new room
  8. Install flooring - stain and finish.
  9. Carpet install (will be done by carpet people)
  10. Move in!!
We have been able to do this with the help of a few friends. Thank you for investing time and energy in our home.
Shalom
Thomas & Tina

Wednesday, April 20, 2011

House update

Hello again after a long time. Just a quick update on the renovation of our house. We are getting very close to being done. Almost all the big construction stuff is out of the way. We have started painting  in the bathrooms upstairs. The upstairs is ready for starting painting. We are trying to get all the remaining small drywall related projects out of the way so that we can avoid dust when we start painting. We still have some electrical wires to be moved and an opening enlarged. (the electrical is the space for the opening). Trim for the new room has to be installed. We are also cleaning up our mess as we go along. Lot of drywall dust and pieces of drywall to be removed. There is a growing pile of construction debris outside that will need to be disposed of. So still a little bit of work to be done. We hope to get move in a couple of months. Here's the list of things to do. If you have the skill and availability we would welcome your assistance.


  1. Cleanup - inside & outside
  2. Move electrical lines and wire new receptacles.
  3. Trim to install - windows, doors, case the openings, crown molding
  4. Exterior window to be cut out and exterior door to be put in it's place.
  5. Spray prime the whole house
  6. Spray paint all the trim
  7. Roll paint in all rooms
  8. Install remaining plumbing fixtures
  9. Install flooring - stain and finish.
  10. Carpet install (will be done by carpet people)
  11. Move in!!
Again - our sincere gratitude to those who have been helping through the past few months.
Shalom
Thomas & Tina